Saturday 26 October 2019

Six years of the Goldsmith's Row cycle counter

August 2019 marked six years since a cycle counter was added onto the newly reconstructed Goldsmith's Row and so it is time for my annual update on the numbers of people cycling along this bicycle only road
As I reported last year the number of people cycling along Goldsmith's Row in the 2017-2018 year was a record low, along with some record low days, weeks and months, so I was keen to see if there had been any increase or if cycling along this road has seen a long term decline. 2018-2019 started well in September, with over 108k people cycling along here; that was an increase of over 8% on September 2017 but still lower than the other four Septembers on record - 16,000 more people cycled along here in September 2014 than they did in September 2018. October saw 113k cycle trips, a big increase again on last year and the highest October of all time. November saw a slight decrease on last year but December was up over 14%, although still the second lowest December recorded.

2019 started well with over 88k cycle trips making it the highest January of all time and February saw a huge increase of over 20% on last year. The "Beast from the East" broke the cycle counter for two months in 2018 so we can't do year-on-year comparisons for March or April. May saw a slight increase on last year but June 2019 was down over 8% on June 2018 and the second lowest June of all time. July 2019 saw record breaking temperatures which tends to bring more people out on their bikes; over 128k people cycled along Goldsmith's Row in this month, the second highest month of all time. 108k cycle trips in August was also a slight increase on last year 

The July heatwave meant that two days from this year made their way into the Top Ten; July 23rd is at No. 7 and July 24th is at No. 9 with temperatures of over 30c on both days. 

Ten highest daily totals:

03/06/14     6624
09/07/15     6380
20/08/13     5825
19/07/16     5817
21/08/13     5785
17/09/13     5778
23/07/19     5776
13/09/16     5706
24/07/19     5668
06/08/15     5643

And Christmas Day last year makes it into No. 9 on the top ten lowest days. The 13 lowest days all fall on either Christmas Day, Boxing Day or New Years Day. 

Ten lowest daily totals:

26/12/17     251
01/01/14     256
26/12/14     292
25/12/15     300
01/01/17     318
26/12/13     321
26/12/16     349
26/12/15     359
25/12/18     368
25/12/16     369

Total for the year is a few thousand short of 1.2 million. Technically a big increase on last year but the counter did not work for two months last year so a year-on-year comparison isn't really possible 



The total number of bicycle trips along Goldsmith's Row for the six year period between 1st September 2013 and 31st August 2019 is 7,059,327 (although two different periods of outages will mean the total will actually be slightly higher than that).

In Summary; more people cycled along Goldsmith's Row this year than they did last year but fewer people are cycling along here in 2017, 2018 and 2019 than they were in 2013, 2014 and 2015. I do wonder if people have switched to other routes since the construction of protected cycle infrastructure under Boris Johnson. I used to cycle along Hackney Road everyday from 2013-2016 but have now switched to CS2 instead, which has seen a 54% increase in cycling according to TfL. It's also interesting to note that even though Goldsmith's Row has been upgraded to a "quietway" and linked with Shoreditch via the Columbia Road quietway this has seen no increase in people using it by bike, quite the opposite. Surely the time has come to finally construct protected cycle tracks on Hackney Road. 

Thursday 17 October 2019

The stonewashing of Worship Street

Worship Street, despite being less than half-a-kilometre long, runs through the boroughs of Islington, Hackney and the City of London. It has been in existence for centuries and is clearly visible in the same location on a 500 year old Tudor map of London, although surrounded by fields, rather than offices as it is today.  As Worship street crosses over from Islington into Hackney it dissects Cycle Superhighway 1 in two with people cycling on CS1 having to give way to motor traffic on Worship Street in order to cycle into the City

Worship Street, where it crosses Paul Street & Wilson Street (Cycle Superhighway 1)
As is clear from the photo above it can be a busy street at times making it difficult for people cycling on CS1 to cross, as many motor vehicles use it as a main route between the Ring Road at Great Eastern Street and City Road, rather than continue on the ring road via the Old Street Roundabout

Worship Street, highlighted in green

You'll note that all traffic using this route has to technically "turn" either right or left and use Curtain road. Whilst Worship Street runs east to west between City Road and Shoreditch High Street (as it has done for over 500 years), motor vehicles have been prohibited from using this direct route for over 25 years. This is due to the IRA Bishopsgate Bombing which resulted in a huge security cordon being placed around the City; initially policemen with traffic cones around the financial district and then a more permanent solution, with nearly 50 streets at the edge of the city sealed off with bollards, leaving them inaccessible for motor traffic but still open for people walking or cycling.

This is how Worship Street looked at the vehicle closure point at the beginning of this year, with a photo I took on New Years Day:

Photo taken from Appold Street in the City of London, looking at Worship Street and Curtain Road, in Hackney 
As you can see there is a narrow through route for bicycles and this is a route I use on a fairly regular basis, if I am cycling on CS1 from dropping my daughter off at school and going to my workplace on the other side of Liverpool Street. Although very quiet in the New Years Day picture above that is not the case at peak time in the morning and you often have to stop and give way to other bicycles, as well as mopeds, coming from the other direction. Worship Street is also generally an unpleasant route to cycle on at peak times as it is very busy with vans, lorries and taxis using it and the road surface is in a terrible state, filled with potholes and sinking manhole covers. Despite using this route dozens of times to cycle from CS1 into the city I didn't notice until I was here on foot on New Years Day that there is also another cycle route on the opposite side of the bollards


This cut through is only really worthwhile if you're coming down from Curtain Road and turning left into Worship Street to head towards Bishopsgate, hence why most people use the other route in both directions instead. You may also notice how the cycleway in the picture above is even narrower, barely wide enough to fit a bike tire in it. This is due to the construction of Principal Place, a newly opened 15 storey office block alongside, built between 2015 and 2018 on long empty land between Curtain Road and Shoreditch High Street, where the disused viaducts into Broad Street station stood until 2014. It also has an enormous 50 storey residential tower alongside it, next to Shoreditch High Street (where over a dozen flats are on the market in excess of £5 million). As part of the planning permission the developers had to contribute various sums to invest in local infrastructure; £10m to Crossrail, £4m for off site affordable housing and various amounts to Hackney Council; from £198k for libraries, £240k for local education and £850k for Highways improvements.

At the beginning of the year Hackney Council decided to invest some of that Highways money to refurbish the area outside, removing the bollards and island in February:


It was a little disappointing to see cyclists dismount signs, considering these were signed as Hackney Council works and there was still a clear route available for people on bikes.


Towards the end of February Worship Street and Curtain Road were closed to motor vehicles altogether either side of the works. A route was kept open through the middle of the works for people walking or cycling


A few days later the "cyclists dismount" sign reappeared even thought the route was signed as "cycle access only" just beyond it.


People continued to cycle through the works and it worked well as a temporary shared route for people walking and cycling, although mopeds were also still using it, which didn't work so well, leading to local police taking action

The following day the "cycle access only" sign was removed and replaced with another cyclists dismount sign. Again, a little disappointing from Hackney Council


By late April Worship Street and Curtain Road had been closed for two months and I'd got used to the quietness. Local businesses seemed unaffected; deliveries were being made by motor traffic either side of the closure whilst the street was filled with the sound of people chatting as they walked; a huge improvement on the motor dominated street it was at the beginning of the year.. There was also an added benefit for people cycling nearby on CS1 - with no through traffic on Worship Street crossing the road became much easier

Three months on from the closure and a sign appeared on Appold Street to say it would be "closed from 20th May for six weeks"


By early June most of the street works seemed to have been completed, but both roads remained closed with cyclists dismount signs on all approaches


In the middle of July Worship street reopened to motor traffic, having been closed as a through route for six months by that point

A street used only by people on foot or bike for six months, Worship Street returns to a street filled with motor traffic using it as a was to avoid the Inner Ring Road
Appold Street remained closed, with cyclists dismount signs still there, for what appeared to be just a toilet parking spot. There was easily the space to allow a cycle route past here





The signs didn't stop the many mopeds from continuing to use this route


By August Appold street was still shut, with the sign at the beginning of the street stating that the closure was in place for "six weeks from May 20th", although the closure had been in place for over three months by that point. As there was actually very little sign of any work taking place I assumed this was due to the wide gaps either side of the new bollards where a motor vehicle could drive through with ease, therefore bypassing the entire ring of steel and driving into the city completely undetected


However at the beginning of September Appold Street finally reopened after four months, with the large gaps either side of the bollards intact, debunking my theory altogether


The bollards were very close together making them a tight fit, I could only just get through with the crate on my front bike so I'm not sure a cargo bike would be able to, although motorbikes could - just about


Then a month later the workmen returned to remove one of the bollards and reconfigure them, to allow slightly larger gaps to cycle through. New bollards were also placed on the footway to plug the gaps

Six bollards became five bollards about a month after work here was completed. Still too narrow for the man on the cargo bike with boxes, who opts for the pavement instead 
Some changes have occurred to Appold and worship Street within the city of London - firstly Worship Street has been resurfaced from Shoreditch High Street and had the contraflow cycle lane painted all the way along it.


Previously you could contraflow cycle along this one way street (for motor traffic) but then have to navigate around a bus stand into oncoming traffic! The contraflow cycle lane continues around the corner to (almost) Primrose Street. The cycle hire stand has also been moved around the corner to accommodate this (although annoyingly the road has not been resurfaced and the former electrical points for the cycle hire stand remain as a line of badly sealed up holes in the tarmac)


Another peeve is that the cycle lane is just a painted lane so naturally I've seen delivery vans parked in it. A kerb protected cycle lane would have been better. It also stops just before the traffic lights at Primrose Street where a "normal" junction with ASL remains, despite this only being accessible by bike (although I've seen black cabs drop off and U-turn here, which could well still be legal)


Despite the cost and time taken for this upgrade Worship Street has not been resurfaced either side of the fancy new paving area, and remains in a terrible state


As for the new paved area of Worship Street, this is the very definition of a stonewashed street







The nearby Leonard Circus has a similar design and looked as good as this on day one but soon had damaged street furniture, now a constant sight

I think these tree cages must have been replaced at least five times each by now
It appears as though some of the street furniture has already been hit on Worship Street, not that anyone particularly wants to sit and eat lunch inches from a lorry tyre! 


It is a real shame that Worship Street was not permanently closed to through motor traffic as part of these works. It was closed for six months and didn't seem to have too much of a drastic effect on surrounding roads. I cycled through and around the closure many times in that period and there was no gridlock or carnage on surrounding streets. A walking and cycling only street, with more trees and benches and an easier crossing on CS1, would have made this a much nicer area than some fancy paving under lorries that should really be using main roads nearby instead.